Feb 11th, 2025 – Day 2 Construction

Foto del escritor: Samantha PatschkeSamantha Patschke

Dear Friends and Supporters,

We are blessed to share an update on the progress of our project. We believe in transparency and honesty, and we want you, our valued donors, to feel confident in the work we’re doing. 🙏

Here’s where we are so far:

✨ Phase 1 is underway! During this phase, we are digging the foundation footing, reinforcing it with rebar, and planting the cross. This is a major step forward, and we are filled with faith and excitement for what’s ahead! 🌱✝️

Our expenses to date:

  • L. 20,167 ($817) on materials (including rebar, cement, and everything needed for the footing and cross) 🛠️

  • L. 5,016 ($203) on labor 💼

  • L. 8,420 ($341) on wood for the cross (this was generously donated, so it didn’t come from our funds—Glory to God! 🙌)

We are moving forward strong! While there’s still much to do, we are excited and confident that God’s powerful hand will continue to move the pieces into place. 🙌✨

Thank you for being an essential part of our ministry! Your support is helping us build something that will make a lasting impact. Together, we are making progress in His name! 💖